Clements Ferry Phase 2 Map
Description:
This project consists of widening Clements Ferry Road for approximately 4.5 miles from Jack Primus Road to SC 41. The improvements involve widening the two-lane roadway to a four-lane curb and gutter section, with a raised planted median and multi-use path along one side of the roadway. This stretch of roadway has a current ADT of 14,200 and includes 2 signalized intersections, approximately 100 properties that will need to be purchased and various utilities that will need to be relocated.
Project Status:
Preliminary engineering activities are underway.  A public information meeting was held on April 27, 2017 at Philip Simmons Middle School which had 123 people in attendance.  An Environmental Assessment has since been completed and is available for review at the link below.  Berkeley County has scheduled a public hearing for April 26, 2018 at Philip Simmons High School from 5:00 to 7:00 to present the preliminary design and effects of the project.  Right of way acquisition is expected to begin in the spring of 2018.  Coordination with utility owners is underway.
 
Comments/questions on the Public Hearing materials shall be accepted through May 11th – send to
Please include your full name, street address, phone number and indicate whether you wish to receive a response to your comment.

 

The above images can be downloaded as a pdf file at this link

 
Design Consultant: ICE Design Status: Underway
ROW Status: Scheduled to begin early 2018 Utility Status: Coordination underway
Construction Contractor: To be determined Construction Status: Scheduled to begin late 2019
Financial Status:
 
  Preliminary Engineering Right-of-Way Construction
Budget $1,800,000 $5,900,000 $34,600,000
Contract $1,242,938 (Right of Way Plans) TBD TBD
Expended to Date $823, 506 0 0
Cost to Complete $976,494 $5,900,000 $34,600,000
Schedule Description:
Design phase is mid Q1, 2016 thru mid Q2, 2017. Right of Way phase is mid Q2, 2017 thru Q2, 2019. Construction phase is Q3, 2019 thru Q2, 2021.

Comments are closed.